Staff presented an $845 million 15-year capital improvement plan for water and wastewater infrastructure, highlighting major challenges and high costs associated with expanding the Crooked Creek treatment plant or managing future growth capacity.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 4, 2026.
Impact analysis
15-year capital program totals approximately $845 million across water and wastewater infrastructure.
County residents and businesses relying on reliable long-term water and wastewater utility service.